A completed job can show an impressive profit when a merchant purchase is attached to the wrong project, a skip invoice is still in an inbox or a subcontractor has not sent the final bill.
Tools2Done gives every recorded expense a clear place in the job record. You can capture the supplier, category, net amount, VAT and total, attach supporting evidence and allocate the cost to the relevant project. That makes it easier to review recorded spending before treating the profitability figure as final.
No system can include a cost that was never entered. Tools2Done helps you organise, allocate and check the costs you have identified so missing records are easier to investigate.
Why an end-of-job cost check matters
Consider a landscaping project sold for £9,500 excluding VAT. Recorded materials, plant, waste and subcontractor costs total £4,600, suggesting a profit of £4,900 and a margin of 51.6%.
The owner then finds:
- A £780 turf and delivery invoice
- A £360 digger hire extension and fuel charge
- A £250 waste-disposal payment recorded without a project
The direct cost rises to £5,990. Profit is £3,510 and the margin is 36.9%.
The problem is not that the calculation was difficult. The calculation used incomplete project costs. A connected job record makes it easier to see what has already been included and what still needs checking.
A practical Tools2Done job cost workflow
Record the commercial detail of the expense
Each expense can include the supplier, category, description, date, payment method, notes, net value, VAT and total. This provides more context than a photograph of a receipt on its own.
Clear descriptions also make the final review faster. An entry such as two-yard skip exchange for Oak Road is more useful than miscellaneous purchase when you are investigating why waste costs exceeded the estimate.
Keep the supporting evidence with the record
Attach the receipt, supplier invoice or other supporting document to the expense. Documents can be uploaded in the usual way, while screenshots can also be pasted from the clipboard.
If the original receipt is missing, the commercial cost should still be investigated and recorded appropriately. Ask the supplier for a replacement invoice or obtain other suitable evidence, and speak to your accountant if you are unsure what is acceptable for bookkeeping or tax purposes.
Allocate direct spending to the correct project
When an expense belongs to a particular job, allocate it to that project. Project-linked spending then contributes to the job's cost and profitability information.
This is particularly useful when the same supplier appears across several jobs. The merchant name alone does not tell you whether a purchase belonged to the bathroom in Leeds, the extension in York or general stock for the van. The project allocation provides that missing commercial context.
Leave genuine overheads outside the job
Not every business cost should be forced onto a project. Insurance, software, rent and other general operating costs can remain unallocated as overheads.
This separation lets you answer two different questions:
- Did this particular job cover its direct costs?
- Does the business as a whole make enough from its jobs to cover its overheads?
Combining both questions into one untidy list makes individual jobs difficult to compare.
Review bank spending where available
Where Open Banking has been enabled and the selected bank is supported, imported transactions remain in a review inbox until the business decides how to treat them.
Outgoing transactions can be matched to existing expenses or used to create a new expense. This helps identify situations where the bank shows that money left the business but the related cost record has not yet been completed.
Banking does not automatically know which project a payment belongs to, and it will not show cash or spending from an unconnected personal card. The business still needs to review and classify each transaction.
Review the project before treating profit as final
Use the project record to review the quoted value, invoicing, payments and recorded project spending. Compare the supplier and cost categories shown with what actually happened on site.
A sensible closeout check asks:
- Have all merchant purchases been entered?
- Are any costs allocated to the wrong project?
- Have final skip, plant and delivery invoices arrived?
- Are all subcontractor invoices included?
- Are returned materials and supplier credits reflected?
- Is known spending still waiting in the bank review inbox?
- Have approved variations and final invoices been handled on the income side?
How different costs should be handled
| Situation | Practical treatment |
|---|---|
| Builders' merchant invoice for one project | Record the expense, attach the invoice and allocate it to that project. |
| Skip invoice arrives after site completion | Add it when received and review the job profit again before treating the result as final. |
| Bank payment already has an expense | Match the transaction rather than creating a duplicate cost. |
| Annual van insurance | Keep it as a general overhead unless the business has a deliberate and consistent allocation policy. |
| Purchase allocated to the wrong job | Correct the project allocation instead of entering the expense twice. |
| Supplier credit expected for returned materials | Follow up the credit and make sure the final cost reflects it. |
What Tools2Done does not do
Tools2Done does not promise to find every lost receipt or automatically discover an invoice that has never been recorded. It also cannot decide the business purpose of an unexplained card payment without input from the user.
Instead, it provides a structured workflow for the costs you identify:
- Record the supplier and category
- Separate net, VAT and total values
- Attach the evidence
- Allocate direct costs to the project
- Keep general overheads separate
- Review bank spending where the banking service is available
- Use the resulting project information to assess profitability
This keeps the software useful without pretending that bookkeeping can be fully accurate without regular input from the business.
Frequently asked questions
Can I record a cost if the paper receipt has been lost?
The cost still needs to be investigated because the money has left the business. Ask the supplier for a replacement invoice or obtain other suitable supporting evidence. Tools2Done allows supporting documents to be attached, but your accountant should advise on evidence and tax treatment where there is uncertainty.
What happens if I record an expense without selecting a project?
The expense remains part of the business records as an unallocated cost or overhead, but it will not contribute to a particular project's cost. If it was genuinely incurred for one job, correcting the project allocation will make that job's profitability view more complete.
Should job profitability use net or gross costs?
Use a consistent basis. VAT-registered businesses often assess commercial margin excluding VAT where that VAT is recoverable. Businesses that are not VAT registered normally experience supplier VAT as part of the cost. Confirm the correct approach for your circumstances with your accountant.
Does bank reconciliation allocate costs automatically?
No. Imported transactions are presented for review. The business decides whether to match them to an expense, create a new expense, identify a transfer or use another appropriate treatment. Availability also depends on Open Banking being enabled and the selected bank being supported.
Should I review costs as soon as the site work finishes?
Run an initial review promptly, but expect some invoices and credits to arrive later. Keep a note of outstanding items and revisit the project before treating its profit as final.
Put recorded costs against the work that created them
Tools2Done connects customer records, projects, expenses, receipts, invoices, payments and profitability information. Instead of judging a job from the sale price or bank balance alone, you can review the commercial record built around the work.
Start with one recently completed project. Add or correct its direct expenses, attach the available evidence and check whether any recorded spending is still sitting outside the job. Then review the profit with a clearer understanding of what the work actually cost.